Esta é uma amostra grátis de 15 questões para a certificação PMP, escrita pela equipe da StudyPDF a partir do exam content outline publicado pelo PMI. Ela funciona como a prova real, com cenários curtos que perguntam o que um gerente de projetos deve fazer primeiro, espalhados pelos domínios People, Process e Business Environment e pelas abordagens preditiva, ágil e híbrida. Responda as 15 questões, depois veja sua pontuação e leia a explicação de cada uma.
A newly formed project team is three weeks in and progress is slow. Two members have been working on the same deliverable without knowing it, and nobody is sure who signs off on anything. What should the project manager do first?
Todos os quizzes de Trabalho e licenças
- Simulado · 15 questões
Simulado SHRM
- Simulado · 15 questões
Simulado CPA
- Simulado · 15 questões
Simulado de corretor de imóveis nos EUA

Crie o seu
Envie seu livro, seus slides ou suas anotações, ou só diga ao Bo o que você quer estudar. Você não precisa de nenhum documento para começar.
Todas as 15 questões de uma vez
Prefere ler antes de jogar? Todas as questões da amostra estão listadas abaixo. As respostas e as explicações ficam fechadas até você abrir.
1. A newly formed project team is three weeks in and progress is slow. Two members have been working on the same deliverable without knowing it, and nobody is sure who signs off on anything. What should the project manager do first?
- A. Ask the sponsor to replace the two members who duplicated work
- B. Work with the team to agree roles, responsibilities and decision rights, and write them down where everyone can see them
- C. Add a buffer to the schedule to absorb the lost time
- D. Wait one more iteration to see whether the team sorts itself out
Mostrar resposta e explicação
Resposta: B. Work with the team to agree roles, responsibilities and decision rights, and write them down where everyone can see them
Duplicated work and unclear sign off are symptoms of undefined roles, not of bad people, so replacing anyone fixes nothing. A new team is still forming, and the project manager's job at that point is to make ownership explicit and visible. Adjusting the schedule treats the symptom and leaves the cause in place.
2. Two senior engineers disagree openly about a technical approach, and the argument is now slowing the whole team. Which conflict approach generally produces the most durable result?
- A. Smoothing, by emphasizing what they agree on and moving past the difference
- B. Withdrawing, by postponing the discussion until tempers cool
- C. Forcing, by deciding for them so the team can move
- D. Collaborating, by working through both positions to a solution each can support
Mostrar resposta e explicação
Resposta: D. Collaborating, by working through both positions to a solution each can support
Collaborating, sometimes called problem solving, is the only approach that deals with the substance of the disagreement, so it tends to hold. The others have their moments. Withdrawing is reasonable when emotions are too high to talk, and forcing is reasonable when safety or a hard deadline leaves no time. Smoothing buries the issue, and buried technical disagreements usually resurface later at a worse moment.
3. Complete the sentence.
In a schedule network, the critical path is the _____ path from start to finish, and the activities on it have _____ of zero.
Opções para a lacuna 1: shortest, longest, most heavily resourced, most expensive
Opções para a lacuna 2: cost variance, lead time, total float, reserve
Mostrar resposta e explicação
Resposta: longest, total float
The critical path is the longest path through the network because it sets the shortest possible duration for the whole project. Activities on it have no total float, so a one day slip on any of them slips the finish date by a day unless you compress the schedule. A project can have more than one critical path, and float can go negative when a date is imposed that the network cannot meet.
4. Halfway through delivery, a department head who was never consulted tells the project manager that the solution will not work for her team. What should the project manager do first?
- A. Explain that requirements are baselined and the project cannot change now
- B. Ask the sponsor to overrule her so the schedule holds
- C. Meet with her to understand her needs and her influence, then update the stakeholder register and the engagement approach
- D. Add everything she asks for to the next release so she stops objecting
Mostrar resposta e explicação
Resposta: C. Meet with her to understand her needs and her influence, then update the stakeholder register and the engagement approach
A stakeholder surfacing this late means the identification and analysis work was incomplete, and the fix is to do it properly rather than to argue about the baseline. Understanding her needs first is what tells you whether this is a real requirement gap, a communication gap or a preference. Whatever comes out of that conversation still goes through change control before it touches the scope.
5. On a predictive project, which of the following make up the scope baseline?
Marque todas as opções corretas.
- A. The project schedule
- B. The project scope statement
- C. The work breakdown structure
- D. The WBS dictionary
- E. The risk register
Mostrar resposta e explicação
Resposta: B. The project scope statement, C. The work breakdown structure, D. The WBS dictionary
The scope baseline is the approved scope statement, the work breakdown structure and the WBS dictionary taken together, and it changes only through formal change control. The schedule and the cost figures are their own baselines. The risk register is a project document that gets updated constantly, so it is never part of a baseline.
6. During a status meeting on a predictive project, the customer asks for one extra feature. The team says it is about two days of work. What should the project manager do?
- A. Record it as a change request so its impact on scope, schedule, cost, quality and risk is assessed and the right people decide
- B. Approve it on the spot, since two days fits inside the contingency reserve
- C. Refuse it, because the scope baseline is approved and cannot be changed
- D. Ask the team to absorb it quietly and keep the reporting unchanged
Mostrar resposta e explicação
Resposta: A. Record it as a change request so its impact on scope, schedule, cost, quality and risk is assessed and the right people decide
Size is not what decides this. Any change to an approved baseline goes through the documented change control process so the impact is assessed and the decision is made by whoever holds that authority, often a change control board. Refusing outright is just as wrong as approving outright, because the process exists to answer the question, not to block it. Absorbing work silently destroys the integrity of the baseline and of your reporting.
7. A project depends on a single supplier with a history of late delivery. The team qualifies a second supplier and moves part of the volume to it. Which risk response strategy is this?
- A. Accept
- B. Mitigate
- C. Avoid
- D. Escalate
Mostrar resposta e explicação
Resposta: B. Mitigate
Mitigating means acting to reduce the probability or the impact of a threat without removing it, and dual sourcing does exactly that, since a late shipment now hurts less. Avoiding would mean changing the plan so the threat cannot occur at all, for example by designing the supplier's component out. Accepting means doing nothing beyond acknowledging the threat, and escalating means handing it to someone outside the project because it sits above your authority.
8. Complete the sentence.
A project has a budget at completion of $200,000. At the checkpoint it is 40 percent complete, $100,000 has been spent, and the planned value is $90,000. The earned value is _____, and the schedule performance index is about _____.
Opções para a lacuna 1: $80,000, $90,000, $100,000, $120,000
Opções para a lacuna 2: 0.80, 0.89, 1.11, 1.25
Mostrar resposta e explicação
Resposta: $80,000, 0.89
Earned value is the share of the work actually finished valued at the budget, so 40 percent of $200,000 is $80,000. Schedule performance index is earned value divided by planned value, which is 80,000 over 90,000, or about 0.89, meaning the project is running behind plan. Cost performance index is earned value divided by actual cost, 80,000 over 100,000, or 0.80, so this project is over budget as well as late.
9. Which statement best describes the difference between quality assurance and quality control?
- A. Assurance is done by the customer and control is done by the team
- B. They are two names for the same set of inspection activities
- C. Assurance is inspecting finished deliverables and control is improving the process
- D. Assurance is about the processes used to produce the work, and control is about checking the results against the requirements
Mostrar resposta e explicação
Resposta: D. Assurance is about the processes used to produce the work, and control is about checking the results against the requirements
Assurance looks at the way work is being done and asks whether the process will reliably produce what was asked for, so audits and process improvement live there. Control looks at the output and asks whether this specific deliverable meets its acceptance criteria, so inspection and measurement live there. Option three has the two swapped, which is the mistake this question is checking for.
10. Which contract type places the most cost risk on the seller rather than the buyer?
- A. Firm fixed price
- B. Cost plus fixed fee
- C. Cost plus incentive fee
- D. Time and materials
Mostrar resposta e explicação
Resposta: A. Firm fixed price
Under a firm fixed price contract the seller commits to a price, so if the work costs more than expected the seller absorbs it. Cost reimbursable contracts move that risk back to the buyer, because the buyer pays the actual costs plus a fee. Time and materials sits in between and is normally used for small or urgent work where the scope is not yet clear enough to price. Fixed price only works when the scope is defined well enough to price it honestly.
11. Which statements about an agile team's product backlog and velocity are accurate?
Marque todas as opções corretas.
- A. The backlog is ordered, so the work judged most valuable sits near the top
- B. Velocity is an average of completed work per iteration and is used to forecast, not to rate people
- C. Items near the top are refined into smaller, clearer pieces than items further down
- D. The backlog is fixed once the project starts, so new items wait for the next project
- E. A team should be given a velocity target and rewarded for beating it
Mostrar resposta e explicação
Resposta: A. The backlog is ordered, so the work judged most valuable sits near the top, B. Velocity is an average of completed work per iteration and is used to forecast, not to rate people, C. Items near the top are refined into smaller, clearer pieces than items further down
A backlog is a living, ordered list, and reordering it as the business learns is the point rather than a failure of planning. Progressive refinement means the near term items are small and well understood while distant items stay coarse, so you do not spend effort detailing work that may never be built. Velocity is a forecasting tool for one team's own planning, and turning it into a target invites inflated estimates, which destroys the forecast.
12. In a retrospective, the team raises the same impediment for the third iteration in a row. What should a project manager acting as a servant leader do?
- A. Note it again and move on, since retrospectives belong to the team
- B. Ask the team to work extra hours to work around it
- C. Take ownership of removing or escalating the impediment, and make the action visible with an owner and a date
- D. Log it in the risk register and review it at the end of the project
Mostrar resposta e explicação
Resposta: C. Take ownership of removing or escalating the impediment, and make the action visible with an owner and a date
Servant leadership means clearing the path so the team can do the work, and an impediment surviving three retrospectives is a signal that nobody owns it. Logging it without acting teaches the team that retrospectives change nothing, which is how teams stop raising problems. Asking for overtime pays for the impediment every iteration instead of removing it once.
13. A program has regulated hardware work and a software product in the same delivery. Which of these are reasonable ways to run it as a hybrid?
Marque todas as opções corretas.
- A. Keep the regulated and hardware work on a plan driven schedule while the software is built in iterations
- B. Use rolling wave planning, so near term work is detailed and later work stays at a high level
- C. Show working software to stakeholders every few weeks while the overall milestone plan stays baselined
- D. Hold daily standups but treat the plan as unchangeable
- E. Skip documentation, since hybrid means the agile rules apply everywhere
Mostrar resposta e explicação
Resposta: A. Keep the regulated and hardware work on a plan driven schedule while the software is built in iterations, B. Use rolling wave planning, so near term work is detailed and later work stays at a high level, C. Show working software to stakeholders every few weeks while the overall milestone plan stays baselined
Hybrid means choosing the approach that fits each part of the work rather than forcing one method onto everything, and regulated or physical work usually needs the predictability of a plan. Rolling wave planning and regular demonstrations let you keep commitments to the business while still learning as you go. The last two options take the ceremonies of agile without the substance, and on regulated work the missing documentation is what fails the audit.
14. Complete the sentence.
The document that says how and when the expected benefits of a project will be measured is the _____, and the person normally accountable for those benefits being realized is the _____.
Opções para a lacuna 1: business case, benefits management plan, project charter, communications management plan
Opções para a lacuna 2: contract administrator, project manager, project sponsor, quality auditor
Mostrar resposta e explicação
Resposta: benefits management plan, project sponsor
The business case argues why the project is worth doing, and the benefits management plan says who measures the resulting benefits, when, and against what baseline. Accountability for realizing them normally sits with the sponsor or a named benefits owner, because most benefits appear after the project has closed. The project manager delivers the outputs and hands over what is needed to measure them, so shipping the full scope on time is not by itself proof of value. Titles vary by organization, so check who your own governance names.
15. Midway through delivery, a new data protection rule takes effect in the country where the product will launch. What should the project manager do first?
- A. Continue as planned, since the requirement was not in the approved scope
- B. Assess the impact on the project and the deliverable with the people who own compliance, then take it through change control
- C. Ask the developers to add whatever they believe the rule requires
- D. Pause the project until someone tells the team what to do
Mostrar resposta e explicação
Resposta: B. Assess the impact on the project and the deliverable with the people who own compliance, then take it through change control
Compliance sits in the Business Environment domain, and the expected behavior is to monitor the external environment, assess the effect on the project and act through the proper channel. The project manager is not the legal expert, so the first move is to get the compliance or legal owner involved and turn their answer into an assessed change. Guessing at a legal requirement is how you build the wrong control and still fail an audit, and doing nothing accepts a risk you have no authority to accept.
O que a prova do PMP cobra de verdade
O PMP é a certificação de gerenciamento de projetos do PMI, e a prova é montada a partir de um documento público chamado exam content outline. Esse documento organiza tudo em três domínios. People cobre liderar e formar um time. Process cobre o trabalho técnico de entregar um projeto, do escopo e do cronograma até risco, qualidade e aquisições. Business Environment cobre como o projeto se conecta à estratégia, à conformidade e ao valor que ele deve produzir. O PMI revisa o documento periodicamente e já mudou tanto os pesos dos domínios quanto a ênfase, então baixe a versão atual em pmi.org em vez de confiar num resumo.
A prova é deliberadamente neutra quanto à abordagem. Uma questão pode te colocar num projeto preditivo, guiado por plano, num time ágil ou num híbrido dos dois, e o documento informa aproximadamente como as questões se dividem entre eles. Não dá para passar nesta prova decorando uma metodologia só. Você tem que perceber em qual ambiente o cenário te colocou e responder de dentro daquele ambiente.
Os números mudam. Quantidade de questões, tempo limite, as horas de experiência em projetos que você precisa para se inscrever, o requisito de escolaridade e a forma como o PMI informa a aprovação são todos definidos pelo PMI e já foram revisados mais de uma vez. Pegue esses dados no PMP handbook atual em pmi.org, e não num blog de estudos.
Como usar esta amostra
Quase toda questão desta prova é um cenário curto, e toda alternativa é algo que um gerente de projetos poderia plausivelmente fazer. É essa a dificuldade toda. Não te perguntam o que é verdade, te perguntam o que você deve fazer primeiro, e as opções normalmente incluem uma que escala cedo demais, uma que pula uma etapa, uma que ignora as pessoas envolvidas, e uma que está certa.
Um método que funciona: leia primeiro a última linha do cenário, porque é ali que a pergunta de verdade está. Depois se posicione, ou seja, qual domínio, qual abordagem de entrega e qual estágio do trabalho. Então elimine. Respostas que não fazem nada, que passam por cima do time, que escalam antes de você ter levantado qualquer fato, ou que aprovam uma mudança sem avaliar o impacto dela estão quase sempre erradas. Respostas que levantam informação, conversam com a pessoa afetada, ou seguem o processo que o time já combinou costumam estar certas.
Faça estas 15 de uma vez, sem anotações, e depois leia todas as explicações, inclusive as das questões que você acertou. Ligue cada erro a uma tarefa do exam content outline, e não a um fato solto. Nada nesta página é orientação jurídica ou financeira. Onde um cenário toca em regulação, o que está sendo cobrado é que você chame as pessoas responsáveis pela conformidade.
Como a StudyPDF cria simulados completos do seu livro de preparação
Quinze questões mostram em qual domínio você está mais fraco. Elas não deixam você pronto sozinhas, e a maioria de quem faz esta prova estuda em volta de um emprego de tempo integral, muitas vezes pagando o curso preparatório do próprio bolso.
A StudyPDF trabalha a partir do material que você já tem. Envie seu livro de preparação para o PMP, os slides do seu provedor de treinamento, suas próprias anotações de processo ou o manual de gerenciamento de projetos da sua empresa, e o Bo, o agente de estudo, cria simulados completos a partir exatamente dessas páginas. Cada questão é baseada no seu material, e cada explicação cita de onde vem a resposta, então, quando algo parecer estranho, dá para ir direto à página e conferir. Você pode gerar um simulado novo quando quiser, restringir a uma área só, como earned value ou engajamento de stakeholders, e acompanhar os conceitos que você continua errando.
Você não precisa de um documento para começar. Se o livro de preparação está em casa e você tem vinte minutos de intervalo, é só dizer um tema, por exemplo estratégias de resposta a riscos ou cerimônias ágeis, e o Bo escreve um simulado sobre isso. Começar é grátis.
Escrito pela equipe da StudyPDF. Atualizado em 2026-08-19.